CSX Railroad Work

Beginning on or around Sunday, May 2, 2021, crews with CSX will begin a tie replacement project in Vincennes.  This work will be performed on the “North-South” line.  Work will begin on 2nd Street and continue through town towards 15th Street.  Work is expected to be completed by the end of the day on Friday, May 7.

There will be approximately 3 different phases of closures.  However, the following crossings will remain open for the duration of the project.  Minneapolis Ave., Washington Ave., Seminary Street, Buntin Street, Perry Street, Main Street and 15th Street.  These crossings can be used at all times.  Phase 1 will be 2nd Street to State Street.  Phase 2 will be State Street to Hart.  Phase 3 will be Hart to 15th.

CSX will be implementing longer work days and additional crews in order to have the crossings opened more quickly than normal.  Please follow the detour routes and be patient this week as work progresses.